Main Street Closure Update After Sewer Collapse at Main Street and Tioronda Avenue
/Main Street One-Lane Update from the City of Beacon
The City Administrator for the City of Beacon, Anthony J. Ruggiero, M.P.A., has issued this update:
There has been a sewer collapse at the intersection of Main Street and Tioronda Avenue.
MAY 10: Starting Thursday, May 10, Main Street will be one lane of traffic from Tioronda Avenue (Howland Cultural Center) to Brothers Restaurant to allow the contractor to start the sewer bypass.
MAY 14 - 16 (approx.): Starting on Monday, May 14, Main Street will be closed to through traffic from Schenck Avenue (Ella's Bellas) to East Main Street (Dummy Light) for approximately three days, until Wednesday, May 16. The contractor will be working through the night to limit the disturbance on this section of Main Street. Parking in this area will be limited.
Sidewalks will remain open.
Notices have been distributed to the business and property owners and appropriate signage will be placed.